§ 13.30.100. Subdivision development.  


Latest version.
  • A.

    The developer of any subdivision requiring a federal or state NPDES stormwater discharge permit will be responsible for obtaining the required permit and developing and implementing an overall SWPPP for the subdivision. Said SWPPP shall include BMPs to be used on individual lot building sites regardless of the issuance of a NOT.

    B.

    City contractors installing public streets; water, sanitary sewer, storm sewer lines; and/or sidewalks will be required to comply with the developers SWPPP and sign the appropriate contractor certification statement. For city contracted work in public right-of-way or easements requiring a federal or state NPDES stormwater discharge permit, the city shall be responsible for obtaining the required permit and preparing the SWPPP, while the city contractor will be responsible for implementing the required SWPPP.

    C.

    Any utility company installing utilities within a new subdivision will also be required to comply with the developers SWPPP and sign the appropriate contractor certification statement. For work in public rights-of-way or easements requiring a federal or state NPDES stormwater discharge permit, the utility company shall be responsible for obtaining the required permit and preparing and implementing the required SWPPP.

    D.

    The purchasers of individual lots within the subdivision shall comply with the developers SWPPP by following the BMPs to be used on individual lot building sites, and shall sign a certification statement agreeing to do so.

(Ord. No. 4205, § 3, 8-17-2009)